Monday, July 31, 2006
Saturday, July 29, 2006
Vinyl, Tile, Fireplace Stone
Concrete steps from garage into house are done.
Vinyl is down in pantry, upstairs bathroom, master bath and laundry room (pictured here).
Master bath.
Full tile backsplash in kitchen--installation in progress.
Fireplace stone has been delivered. Will be installed on Monday. Large gray squares are hearthstones.
A few of the pieces that will be on the face of the fireplace. Interesting variation of color.
Thursday, July 27, 2006
Wednesday, July 26, 2006
More finish surfaces going down...
Laminate is here for countertops (laying on the floor).
Holes are cut in countertops for sinks.
Back porch, less loaded up with stuff.
Masking has been removed, so trim contrast shows up with mocha walls. Very nice trim paint job--so shiny and smooth.
Fireplace frontpiece has been installed.
Windowboxes are planted and ready to be put in place. Hopefully we'll have some fluff before the season's over.